Who supplies and pays for the electricity behind AI data centers?
Filed By irfolks
Economics Desk3 min read
945 TWh. That’s the IEA’s estimate of how much electricity the world’s data centers will use by 2030, roughly double today. In Indonesia, data center capacity is around 580 to 630 MW right now, with another 1.3 GW waiting in the queue. Who’s going to supply all that power, and who pays for it?
The government has started asking big data center investors to bring their own power, while PLN, the state utility, wants prices that work for PLN. That comes from a Danantara representative.
Double in six years
The 945 TWh figure comes from an IEA report published on 10 April 2025. According to the report, demand from AI-optimized data centers will more than quadruple by 2030. In the US, data centers are expected to account for almost half of the growth in electricity demand. In Japan, more than half. In Malaysia, up to a fifth.
The IEA expects renewables and natural gas to meet most of that demand, because they’re cheap and available in the major markets. Keep in mind this is a 2025 projection, so newer numbers could differ.
Indonesia’s queue is already long
According to Kontan (13 September 2026), the data center operators’ association IDPRO recorded operating capacity of around 630 MW as of May 2026. ICT Institute put it at about 580 MW. Both agree on a queue of around 1.3 GW. IDPRO expects 2026 demand to grow 35 to 45%.
Supply commitments mentioned include 511 MVA for DayOne in Batam and more than 1 GW for BDx across several sites.
The scale only sinks in when you compare it. The energy ministry projects data center demand of around 32 GW by 2032, while national installed generation capacity is around 109 GW as of July 2026.
Bring your own power, or borrow the grid
Stefanus Ade Hadiwidjaja of Danantara Indonesia said on 22 October 2026 that data centers above 500 MW must bring their own energy. The reason is to keep supply for industry and households from shrinking. Smaller projects can still use the public grid, with allocation and tariffs following PLN policy, which he said must be “profitable for PLN”. Power purchase contracts typically run 10 to 15 years.
The head of IDPRO put more weight on knowing when the first grid connection will be available than on cheaper tariffs. Kontan also noted the risks. Capacity could end up in oversupply if the queue is built too fast, and electricity alone isn’t enough because transmission lines, substations, land, and cooling water are needed too.
Does your home electricity get hit?
This is our own reasoning, with no source. Household electricity tariffs are being held by the government, and the state pays the cost gap. If data center demand rises faster than new power plants come online, the worry Danantara described could show up, with supply for industry and households getting tighter. We haven’t found data showing that’s happened. The bring-your-own-power rule is meant to keep that burden off the public grid.
How to read numbers in data center news
This is our own advice. Check the unit first. MW or GW is power, how much electricity can be used at once. GWh or TWh is energy, what gets used over a period of time. The two get mixed up in headlines all the time. Then ask two things: is the power coming from the public grid or a plant of their own, and who pays if new plants or grid lines have to be built.
Sources
- AI is set to drive surging electricity demand from data centres, International Energy Agency, 10 April 2025
- Energy and AI, International Energy Agency, 10 April 2025
- Investasi Data Center Berpacu dengan Pertumbuhan Permintaan, Kontan, 13 September 2026
- Danantara Minta Data Center di Atas 500 MW Punya Pasokan Energi Sendiri, KabarBursa, 24 October 2026